Third Mainland Bridge: FG gives update on total shutdown

Advertisements

Mr Olukayode Popoola, the Federal Controller of Works Lagos State, has said that the total shutdown of the Third Mainland Bridge would be lifted at midnight 24 hours ahead of schedule.

Popoola told the News Agency of Nigeria (NAN) on Sunday in Lagos that the total shutdown had to be lifted because the contractor was able to fast track the delicate task they needed to execute.

He explained that the initially scheduled 72 hours timeframe was achieved within 48 hours, hence the reopening to traffic 24 hours ahead of schedule.

“We have completed the casting of the three number expansion joints on the Third Mainland Bridge.

“Therefore, the bridge shall be opened at 12:00 midnight Sunday, Dec. 27 and no longer Monday, Dec. 28.

“That is 48 hours and no more 72 hours,” Popoola said.

thedabigal reports that the controller had on Tuesday, Dec. 22 announced a 72 hours total shutdown of the bridge with effect from midnight on Saturday to midnight Tuesday.

The shutdown was to stop vibrations caused by the movement of vehicles for contractors to cast concrete on additional three expansion joints in the ongoing rehabilitation of the bridge.

Related posts

Actor Adeniyi Johnson and wife Seyi Edun welcome twins after 7 years of waiting

Hope Odabi

“If your boyfriend speaks ill of a particular girl to you, the chances that he is sleeping with her is 90%” – Actress, Aniebiet Francis says

Hope Odabi

Man accidentally cuts off his ‘SOMETHING’ while dreaming about cutting meat

Hope Odabi

Leave a Comment

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More